ARCHIVED General Condition (GC) 5 - Terms of Payment - <100K - Construction Services

Attention! We’ve Moved! The Supply Manual has moved to the CanadaBuys website. Check out the new landing page for the Supply Manual.

Attention! As part of the Acquisitions Program’s transformation agenda, PSPC is planning to archive and migrate the SACC manual to the CanadaBuys website. The SACC manual will continue to be available on the BuyandSell website to ensure continuity of service during this transition period. At this time, an initial version of the archived version of the SACC has been posted on CanadaBuys. We encourage you to go visit the site and get comfortable with the new format of the SACC at the following:

Archived - Standard Acquisition Clauses and Conditions Manual | CanadaBuys

We appreciate your continued feedback and cooperation during this transition.

Archived Content

Information identified as archived is provided for reference, research or recordkeeping purposes. It is not subject to the Government of Canada Web Standards and has not been altered or updated since it was archived. Please contact us to request a format other than those available.

Legal text for SACC item

GC5.1 (2007-05-25) Interpretation

In these Terms of Payment

The "payment period"
means a period of 30 consecutive days or such other longer period as may be agreed between the Contractor and Canada.
An amount is "due and payable"
when it is due and payable by Canada to the Contractor according to GC5.4, "Progress Payment", GC5.5, "Substantial Performance of the Work", or GC5.6, "Final Completion".
An amount is "overdue"
when it remains unpaid on the first day following the day upon which it is due and payable.
The "date of payment"
means the date of the negotiable instrument of an amount due and payable by the Receiver General for Canada.
The "Bank Rate"
means the rate of interest established by the Bank of Canada as the minimum rate at which it makes short term advances to members of the Canadian Payments Association.
The "Average Bank Rate"
means the simple arithmetic mean of the Bank Rate in effect at 4:00 p.m. Eastern Standard Time each day during the calendar month which immediately precedes the calendar month in which payment is made.

GC5.2 (2010-01-11) Amount Payable

  1. Subject to any other provisions of the Contract, Canada shall pay the Contractor, at the times and in the manner hereinafter set out, the amount by which the amounts payable by Canada to the Contractor in accordance with the Contract exceed the amounts payable by the Contractor to Canada, and the Contractor shall accept that amount as payment in full satisfaction for everything furnished and done by the Contractor in respect of the Work to which the payment relates.
  2. When making any payment to the Contractor, the failure of Canada to deduct an amount payable to Canada by the Contractor shall not constitute a waiver of the right to do so, or an admission of lack of entitlement to do so in any subsequent payment to the Contractor.
  3. Should any payment be made by Canada in excess of what is owed to the Contractor for the actual work performed, the Contractor will reimburse Canada the excess immediately, with or without demand, and any amounts outstanding shall bear simple interest at the Average Bank rate plus 3 percent per annum from the date of overpayment until the day prior to the date of repayment by the Contractor.
  4. No payment other than a payment that is expressly stipulated in the Contract shall be made by Canada to the Contractor for any extra expense or any loss or damage incurred or sustained by the Contractor.

GC5.3 (2014-06-26) Increased or Decreased Costs

  1. The Contract Amount shall not be increased nor decreased by reason of any increase or decrease in the cost of the Work that is brought about by an increase or decrease in the cost of labour, Plant, Material or any wage adjustment.
  2. Notwithstanding paragraph 1) of GC5.3, if any change, including a new imposition or repeal, of any tax, customs or other duty, charge, or any similar imposition that is imposed under sales, customs or excise tax legislation of the Government of Canada or any Provincial or Territorial legislation, affects the cost of the Work to the Contractor, and occurs
    1. after the date of submission by the Contractor of its bid; or
    2. after the date of submission of the last revision, if the Contractor's bid was revised;
    the Contract Amount shall be adjusted in the manner provided in paragraph 3) of GC5.3.
  3. If a change referred to in paragraph 2) of GC5.3 occurs, the Contract Amount shall be increased or decreased by an amount established by an examination by Canada of the relevant records of the Contractor referred to in GC2.8, "Accounts and Audits", to be the increase or decrease in the cost incurred by the Contractor that is directly attributable to that change.
  4. For the purpose of paragraph 2) of GC5.3, if a tax is changed after the tender closing, but public notice of the change has been given by the Minister of Finance or the corresponding Provincial or Territorial authority before that closing, the change shall be deemed to have occurred before the solicitation closing.
  5. Notwithstanding paragraphs 2) to 4) of GC5.3, no adjustment to the Contract Amount in respect of the Work or a part thereof shall be made for a change in any imposition referred to in this section that occurs after the date required by the Contract for completion of the Work or that part of the Work.

GC5.4 (2014-06-26) Progress Payment

  1. Where the duration of the Work is greater than thirty (30) days, the Contractor shall be entitled to receive progress payments.
  2. On the expiration of a payment period, the Contractor shall deliver to Canada
    1. a written progress claim in a form acceptable to Canada that fully describes any part of the Work that has been completed, and any Material that was delivered to the Work site but not incorporated into the Work, during that payment period, and
    2. a completed and signed statutory declaration containing a declaration that, up to the date of the progress claim, the Contractor has complied with all lawful obligations and that, in respect of the Work, all lawful obligations of the Contractor to its Subcontractors and Suppliers, referred to collectively in the declaration as "subcontractors and suppliers", have been fully discharged.
  3. Within 10 days of receipt of a progress claim and statutory declaration from the Contractor, Canada shall inspect, or cause to have inspected, the part of the Work and the Material described in the progress claim, and shall issue a progress report to the Contractor, that indicates the value of the part of the Work and the Material described in the progress claim that, in the opinion of Canada
    1. is in accordance with the Contract; and
    2. was not included in any other progress report relating to the Contract.
  4. Subject to GC5.2, and paragraph 6) of GC5.4, Canada shall pay the Contractor an amount that is equal to 90 percent of the value that is indicated in Canada's progress report.
  5. Canada shall pay the amount referred to in paragraph 4) of GC5.4 not later than
    1. 30 days after receipt by Canada of both a progress claim and a statutory declaration referred to in paragraph 2) of GC5.4; or
    2. 15 days after receipt by Canada of the Contractor's progress schedule or updated progress schedule, in accordance with GC3.1, "Progress Schedule",
    whichever is later.
  6. In the case of the Contractor's first progress claim, it is a condition precedent to Canada's obligation under paragraph 4 of GC5.4 that the Contractor has provided all necessary documentation required by the Contract for the first progress claim.
  7. Where the duration of the Work is equal to or less than thirty (30) days, the Contractor shall, following the issuance of a Certificate of Completion in accordance with GC5.6, "Final Completion", receive a single payment as full consideration for the Work performed.

GC5.5 (2014-06-26) Substantial Performance of the Work

  1. If, at any time before the issuance of a Certificate of Completion, Canada determines that the Work has reached Substantial Performance as described in subparagraph 1) (b) of GC1.1.4, "Substantial Performance", Canada may issue a Certificate of Substantial Performance to the Contractor. The Certificate of Substantial Performance shall state or describe
    1. the date of Substantial Performance;
    2. the parts of the Work not completed to the satisfaction of Canada; and
    3. all things that must be done by the Contractor before a Certificate of Completion is issued and before the 12-month warranty period referred to in GC3.13, "Warranty and Rectification of Defects in Work", commences for the said parts and all the said things.
  2. The issuance of a Certificate of Substantial Performance does not relieve the Contractor from the Contractor's obligations under GC3.11, "Defective Work".
  3. Subject to GC5.2, "Amount Payable" and paragraph 4) of GC5.5, Canada shall pay the Contractor the amount referred to in paragraph 1) of GC5.2, "Amount Payable", less the aggregate of
    1. the sum of all payments that were made pursuant to GC5.4, "Progress Payment";
    2. an amount that is equal to Canada's estimate of the cost to Canada of rectifying defects described in the Certificate of Substantial Performance; and
    3. an amount that is equal to Canada's estimate of the cost to Canada of completing the parts of the Work described in the Certificate of Substantial Performance other than defects listed therein.
  4. Canada shall pay the amount referred to in paragraph 3) of GC5.5 not later than
    1. 30 days after the date of issue of a Certificate of Substantial Performance, or
    2. 15 days after the Contractor has delivered to Canada
      1. a statutory declaration containing a declaration by the Contractor that up to the date of the Certificate of Substantial Performance, the Contractor has complied with all lawful obligations, discharged all its lawful obligations to its Subcontractors and Suppliers in respect of the work under the Contract, and discharged its lawful obligations referred to in GC1.8, "Laws, Permits and Taxes";
      2. evidence of compliance with workers' compensation legislation in accordance with GC1.9, "Workers' Compensation"; and
      3. an update of the progress schedule in accordance with the requirements of GC3.1, "Progress Schedule";
      whichever is later.

GC5.6 (2008-05-12) Final Completion

  1. When Canada is of the opinion that the Contractor has complied with the Contract and all orders and directions made pursuant thereto, and that the Work has been completed as described in GC1.1.5, "Completion", Canada shall issue a Certificate of Completion to the Contractor and, if the Work or a portion of the Work is subject to a Unit Price Arrangement, Canada shall issue a Certificate of Measurement that shall, subject to GC8, be binding upon and conclusive between Canada and the Contractor as to the quantities referred to therein.
  2. Subject to GC5.2, "Amount Payable", and paragraph 3) of GC5.6, Canada shall pay the Contractor the amount referred to in GC5.2, "Amount Payable", less the aggregate of the sum of all payments that were made pursuant to GC5.4, "Progress Payment", and GC5.5, "Substantial Performance of Work".
  3. Canada shall pay the amount referred to in paragraph 2) of GC5.6 not later than
    1. 30 days after the date of issue of a Certificate of Completion; or
    2. 15 days after the Contractor has delivered to Canada
      1. a statutory declaration which contains a declaration by the Contractor that all of the Contractor's lawful obligations and any lawful claims against the Contractor that arose out of the performance of the Contract have been discharged and satisfied; and
      2. evidence of compliance with workers' compensation legislation in accordance with GC1.9, "Workers' Compensation";
      whichever is later.

GC5.7 (2015-02-25) Payment not Binding on Canada

Neither acceptance of a progress claim or progress report, nor any payment made by Canada under the Contract, nor partial or entire use or occupancy of the Work by Canada shall constitute an acceptance by Canada of any portion of the Work or Material that is not in accordance with the requirements of the Contract.

GC5.8 (2008-05-12) Claims and Obligations

  1. The Contractor shall discharge all the Contractor's lawful obligations and shall satisfy all lawful claims against the Contractor arising out of the performance of the Work at least as often as the Contract requires Canada to pay the Contractor.
  2. Whenever requested to do so by Canada, the Contractor shall make a statutory declaration declaring to the existence and condition of any obligations and claims against the Contractor arising out of the performance of the Work.
  3. In order to discharge lawful obligations of and satisfy lawful claims against the Contractor or its Subcontractors arising out of the performance of the Contract, Canada may pay an amount that is due and payable to the Contractor directly to the claimant. Such payment is, to the extent of the payment, a discharge of Canada's liability to the Contractor under the Contract and may be deducted from any amount payable to the Contractor under the Contract.
  4. For the purposes of paragraph 3) of GC5.8, and subject to paragraph 6) of GC5.8, a claim or obligation shall be considered lawful when it is so determined by
    1. a court of legal jurisdiction;
    2. an arbitrator duly appointed to arbitrate the claim; or
    3. the written consent of the Contractor authorizing payment of the claim or obligation.
  5. If a claim or obligation would have been subject to the provisions of Provincial or Territorial lien legislation or, in the Province of Quebec, the law relating to legal hypothecs had the Contractor been performing the Work for an entity other than Canada
    1. such amount as may be paid by Canada pursuant to paragraphs 3) and 4) of GC5.8 shall not exceed the amount that the Contractor would have been obliged to pay had the provisions of such legislation or law been applicable to the Work;
    2. a claimant need not comply with the provisions of such legislation, setting out the steps by way of notice, registration or otherwise as might have been necessary to preserve or perfect any claim for lien or privilege which the claimant might have had; and
    3. for the purposes of determining the entitlement of a claimant, the notice required by paragraph 8) of GC5.8 shall be deemed to replace the registration or provision of notice after the performance of work as required by any applicable legislation and no claim shall be deemed to have expired, become void or unenforceable by reason of the claimant not commencing any action within the time prescribed by such legislation.
  6. The Contractor shall, at the request of any claimant, submit to binding arbitration those questions that need to be answered to establish the entitlement of the claimant to payment. The arbitration shall have as parties to it any Subcontractor or Supplier to whom the claimant supplied Material, performed work or rented equipment should such Subcontractor or Supplier wish to be adjoined, and Canada shall not be a party to such arbitration. Subject to any agreement between the Contractor and the claimant, the arbitration shall be conducted in accordance with the governing Provincial or Territorial legislation applicable to the site of the Work.
  7. Paragraph 3) of GC5.8 shall apply only to claims and obligations
    1. the notification of which has set forth the amount claimed to be owing and the person who by contract is primarily liable and has been received by Canada in writing before final payment is made to the Contractor pursuant to GC5.6, "Final Completion", and within 120 days of the date on which the claimant
      1. should have been paid in full under the claimant's contract with the Contractor, its Subcontractor or Supplier if the claim is for money that was lawfully required to be held back from the claimant; or
      2. performed the last of the services, work or labour, or furnished the last of the Material pursuant to the claimant's contract with the Contractor or its Subcontractor or Supplier where the claim is for money not lawfully required to be held back from the claimant; and
    2. the proceedings to determine the right to payment of which, pursuant to paragraph 5 of GC5.8, shall have commenced within one year from the date that the notification required by subparagraph 7)(a) of GC5.8 was received by Canada.
  8. Upon receipt of a notice of claim, Canada may withhold, from any amount that is due and payable to the Contractor pursuant to the Contract, the full amount of the claim or any portion thereof.
  9. Canada shall notify the Contractor in writing in a timely manner of receipt of any claim and of the intention of Canada to withhold funds. At any time thereafter and until payment is made to the claimant, the Contractor may be entitled to post, with Canada, security in a form acceptable to Canada in an amount equal to the value of the claim, and upon receipt of such security Canada shall release to the Contractor any funds that would be otherwise payable to the Contractor, that were withheld pursuant to the provisions of this clause in respect of the claim of any claimant for whom the security stands.

GC5.9 (2008-05-12) Right of Setoff

  1. Without limiting any right of setoff or deduction given or implied by law or elsewhere in the Contract, Canada may set off any amount payable to Canada by the Contractor under the Contract, or under any current contract, against any amount payable to the Contractor under the Contract.
  2. For the purposes of paragraph 1) of GC5.9, "current contract" means a contract between Canada and the Contractor
    1. under which the Contractor has an undischarged obligation to perform or supply work, labour or material; or
    2. in respect of which Canada has, since the date of the Contract, exercised any right to take the work that is the subject of that contract out of the Contractor's hands.

GC5.10 (2007-05-25) Assessments and Damages for Late Completion

  1. For the purposes of this clause
    1. the Work shall be deemed to be completed on the date of the Certificate of Completion; and
    2. the "period of delay" means the number of days commencing on the day fixed for completion of the Work and ending on the day immediately preceding the day on which the Work is completed but does not include any day within a period of extension granted pursuant to GC6.5, "Delays and Extension of Time", and any other day on which, in the opinion of Canada, completion of the Work was delayed for reasons beyond the control of the Contractor.
  2. If the Contractor does not complete the Work by the day fixed for its completion but completes it thereafter, the Contractor shall pay Canada an amount equal to the aggregate of
    1. all salaries, wages and travelling expenses incurred by Canada in respect of persons overseeing the performance of the Work during the period of delay;
    2. the cost incurred by Canada as a result of the inability to use the completed Work for the period of delay; and
    3. all other expenses and damages incurred or sustained by Canada during the period of delay as a result of the Work not being completed by the day fixed for its completion.
  3. Canada may waive the right of Canada to the whole or any part of the amount payable by the Contractor pursuant to paragraph 2) of GC5.10 if, in the opinion of Canada, it is in the public interest to do so.

GC5.11 (2008-05-12) Delay in Making Payment

  1. Notwithstanding GC1.5, "Time of the Essence", any delay by Canada in making any payment when it is due pursuant to GC5, "Terms of Payment", shall not be a breach of the Contract by Canada.
  2. Subject to paragraph 3) of GC5.11, Canada shall pay to the Contractor simple interest at the Average Bank Rate plus 3 percent per annum on any amount that is overdue pursuant to paragraph 3) of GC5.1, "Interpretation", and the interest shall apply from and include the day such amount became overdue until the day prior to the date of payment.
  3. Interest shall be paid without demand by the Contractor except that
    1. in respect of amounts that are less than 15 days overdue, no interest shall be paid in respect of payment made within such 15 days unless the Contractor so demands after such amounts have become due and payable; and
    2. interest shall not be payable or paid on overdue advance payments, if any.

GC5.12 (2008-05-12) Interest on Settled Claims

  1. For the purposes of this clause, a claim means a disputed amount subject to negotiation between Canada and the Contractor under the Contract.
  2. A claim is deemed to have been settled when an agreement in writing is signed by Canada and the Contractor setting out the amount of the claim to be paid by Canada and the items of work for which the said amount is to be paid.
  3. A settled claim is deemed to be outstanding from the day immediately following the date the said claim would have been due and payable under the Contract had it not been disputed.
  4. Canada shall pay to the Contractor simple interest on the amount of a settled claim at the Average Bank Rate plus 3 percent per annum from the date the settled claim was deemed to be outstanding until the day prior to the date of payment.