Project Schedule - Bid

Attention! We’ve Moved! The Supply Manual has moved to the CanadaBuys website. Check out the new landing page for the Supply Manual.

Legal text for SACC item

  1. As part of its technical bid, the Bidder must propose its preliminary project schedule, in __________ (insert "network", "Gantt chart" or "detailed bar chart") format. The project schedule must include the Bidder's work breakdown structure, the scheduling of main activities and milestone events, and any potential problem areas involved in completing the Work.
  2. The Bidder's schedule must also provide a target date for each of the following significant events:
    1. _________;
    2. _________;
    3. _________;
    4. _________;
    5. _________;
    6. _________;
    7. _________.