ARCHIVED Managing Urgent Acquisitions

Attention! We’ve Moved! The Supply Manual has moved to the CanadaBuys website. Check out the new landing page for the Supply Manual.

Attention! We’ve Moved! The SACC has been archived and moved to the CanadaBuys website. Check out the new landing page for the archived SACC manual

Archived Content

Information identified as archived is provided for reference, research or recordkeeping purposes. It is not subject to the Government of Canada Web Standards and has not been altered or updated since it was archived. Please contact us to request a format other than those available.

Item Information

Introduction

The purpose of Policy Notification 102 (PN-102) is to update the instructions to contracting officers on the process to acquire goods and services when there is an urgent requirement.

Effective Date

This PN is effective immediately.

Revisions to the Current Policy

This PN establishes a new section in the Supply Manual on Urgent Acquisitions.  The detailed Supply Manual changes are contained in Annex A.

Contact Persons

For more information, contact Heather Bartlett, by phone at 819-956-0912 or by e-mail at: heather.bartlett@tpsgc-pwgsc.gc.ca.

Annex A

3.21 Managing Urgent Acquisitions

  1. An urgent requirement (acquisition) is one that calls for immediate action and conveys a sense of urgency. The contracting officer will decide, in consultation with the client and PWGSC management as required, if the requirement is to be treated as an urgent acquisition. Defining an acquisition as urgent will depend on the current client department's priorities as well as government priorities as a whole. For example, an urgent requirement may be defined as those acquisitions where an undue delay could have a significant economic impact, an effect on health and safety programs, or a risk of not meeting an important project/program milestone.
  2. In most cases, it is important that PWGSC be engaged early in the process, respecting roles and responsibilities, to ensure that a comprehensive procurement strategy is developed to meet the client's operational objectives.
  3. When the requirement has been identified as urgent, the following strategies may be utilized:
    1. PWGSC and the client should use an integrated team approach with dedicated personnel working closely with the client's project team. Where there are multiple urgent requirements, consideration should be given to having a single point of contact in each department to coordinate all of the acquisitions.
    2. Early development of sound communication channels is crucial, involving all stakeholders. Urgent requirements will be given priority attention, and concurrent review processes should be established and used whenever possible.
    3. Contracting officers should provide information to the industry as early as possible in the process, using such pre-solicitation tools as Request for Information (RFI), Solicitation of Interest and Qualification (SOIQ), and Price and Availability Enquiries (P&A), where appropriate. For more information on the use of these tools, see 4.5.
    4. In cases where Treasury Board project approval is required but has not yet been obtained by the client, consideration must be given to developing a joint TB submission signed by both ministers that will seek (advance) contract approval at the same time. The TBS program sector analyst should always be contacted prior to finalization of the TB submission for advice and guidance in regards to the content and on the approval process.