Legal text for SACC item
- To be declared responsive, a bid must:
- comply with all the requirements of the bid solicitation;
- meet all mandatory criteria, including being registered on the Inuit Firm Registry (IFR);
(if applicable, choose one of the options below)
Option 1
- obtain the required minimum of _______ (insert minimum number of points) points overall for the technical evaluation criteria which are subject to point rating.
The rating is performed on a scale of ___________ (insert total number of available points) points.
Or
Option 2
- obtain the required minimum points specified (choose "for each criterion" or "for criterion number ___" or "for criteria numbers ___, ___") for the technical evaluation, and
- obtain the required minimum of ____ (insert minimum number of points) points overall for the technical evaluation criteria which are subject to point rating.
The rating is performed on a scale of ____ (insert total number of available points) points.
- Bids not meeting the requirements specified in Section 1 will be declared non-responsive.
- The selection will be based on the highest responsive combined rating of total Inuit Benefits Plan (IBP) merit, (if applicable, insert “technical merit,”) and price. The ratio will be 30% for the total IBP merit, (if applicable, insert “ __% (percentage for technical merit) for the technical merit”) and __% (insert percentage for price) for price.
If applicable, Insert 4. Otherwise delete and renumber accordingly
- To establish the technical merit score, the overall technical score for each responsive bid will be determined as follows: total number of points obtained / maximum number of points available, multiplied by the ratio of ___ (insert percentage value for technical merit).
- To establish the pricing score, each responsive bid will be prorated against the lowest evaluated price and the ratio of ___% (insert percentage for price) as follows: lowest evaluated price / bid price, multiplied by the ratio of ___ (insert percentage value for price).
- The IBP merit score for each criterion will be determined as follows: The total number of points obtained for that criterion / maximum number of points available for that criterion, multiplied by the percentage ratio applicable for that criterion.
- The total IBP merit score is the combined sum total of all individual IBP merit scores.
(Insert applicable options from the list below. Contracting Authorities (CAs) must ensure that percentages are in accordance with the Nunavut Directive)
- Inuit Employment ___% (insert percentage for Inuit Employment)
- Inuit Training and Skills Development ___% (insert percentage for Inuit Training and Skills Development)
- Inuit Ownership (Contractor and subcontractors) ___% (insert percentage for Inuit Ownership (Contractors and subcontractors))
- Location in the Nunavut Settlement Area (NSA) ___% (insert percentage for location in the Nunavut Settlement Area (NSA))
- For each responsive bid, the total IBP merit score for each criterion, (If applicable, insert “the technical merit score,”) and the pricing score will be added to determine its combined rating.
- Neither the responsive bid obtaining the highest technical score nor the one with the lowest evaluated price will necessarily be accepted. The responsive bid with the highest combined rating of total IBP merit score, (if applicable, insert “technical merit score,”) and pricing score will be recommended for award of a contract. In the case of a tie, the bid with the lower price will be selected.
(Insert the applicable option below, based on whether technical criteria will be point rated)
Option 1
The table below illustrates an example where all three bids are responsive and the selection of the contractor is determined by a 30/45/25 ratio of total IBP merit score, technical merit score, and pricing score, respectively. In this example, Inuit employment is weighted at 10%, Inuit Training and Skills Development is weighted at 10%, Inuit Ownership (Contractor and subcontractors) is weighted at 5%, and Location in the Nunavut Settlement Area (NSA) is 5%. Note that this is for illustrative purposes only and the values for the present solicitation may differ.
Bidder 1 | Bidder 2 | Bidder 3 | ||
---|---|---|---|---|
Overall Technical Score | 90/100 | 85/100 | 95/100 | |
Bid Evaluated Price | $16,000 | $17,000 | $20,000 | |
Inuit Benefits Plan | Inuit Employment Score | 31.75/40 | 32.75/40 | 33.75/40 |
Inuit Training Score | 5/15 | 10/15 | 15/15 | |
Inuit Ownership Score | 15/40 | 35/40 | 25/40 | |
Location in NSA Score | 10/10 | 10/10 | 10/10 | |
Calculations: Technical Merit & Price | Technical Merit Score | 90/100 x 45 = 40.5 | 85/100 x 45 = 38.25 | 95/100 x 45 = 42.75 |
Pricing Score | 16/16 x 25 = 25 | 16/17 x 25 = 23.53 | 16/20 x 25 = 20 | |
Calculations: Total IBP Merit Score | Inuit Employment Merit Score | 31.75/40 x 10 = 7.94 | 32.75/40 x 10 = 8.19 | 33.75/40 x 10 = 8.44 |
Inuit Training Merit Score | 5/15 x 10 = 3.33 | 10/15 x 10 = 6.67 | 15/15 x 10 = 10 | |
Inuit Ownership Merit Score | 15/40 x 5 = 1.88 | 35/40 x 5 = 4.38 | 25/40 x 5 = 3.13 | |
Location in NSA Merit Score | 10/10 x 5 = 5.0 | 10/10 x 5 = 5.0 | 10/10 x 5 = 5.0 | |
Combined Rating | 83.65 | 86.02 | 89.32 | |
Overall Rating | 3rd | 2nd | 1st |
Or
Option 2
The table below illustrates an example where all three bids are responsive and the selection of the contractor is determined by a 30/70 ratio of total IBP merit score and pricing score, respectively. In this example, Inuit employment is weighted at 10%, Inuit Training and Skills Development is weighted at 10%, Inuit Ownership (Contractor and subcontractors) is weighted at 5%, and Location in the Nunavut Settlement Area (NSA) is 5%. Note that this is for illustrative purposes only and the values for the present solicitation may differ.
Bidder 1 | Bidder 2 | Bidder 3 | ||
---|---|---|---|---|
Bid Evaluated Price | $16,000 | $17,000 | $20,000 | |
Inuit Benefits Plan | Inuit Employment Score | 31.75/40 | 32.75/40 | 33.75/40 |
Inuit Training Score | 5/15 | 10/15 | 15/15 | |
Inuit Ownership Score | 15/40 | 35/40 | 25/40 | |
Location in NSA Score | 10/10 | 10/10 | 10/10 | |
Calculations: Price | Pricing Score | 16/16 x 70 = 70 | 16/17 x 70 = 65.90 | 16/20 x 70 = 56 |
Calculations: Total IBP Merit Score | Inuit Employment Merit Score | 31.75/40 x 10 = 7.94 | 32.75/40 x 10 = 8.19 | 33.75/40 x 10 = 8.44 |
Inuit Training Merit Score | 5/15 x 10 = 3.33 | 10/15 x 10 = 6.67 | 15/15 x 10 = 10 | |
Inuit Ownership Merit Score | 15/40 x 5 = 1.88 | 35/40 x 5 = 4.38 | 25/40 x 5 = 3.13 | |
Location in NSA Merit Score | 10/10 x 5 = 5.0 | 10/10 x 5 = 5.0 | 10/10 x 5 = 5.0 | |
Combined Rating | 88.15 | 90.14 | 82.57 | |
Overall Rating | 2nd | 1st | 3rd |