Cancellation of Stop Work Order

Attention! We’ve Moved! The Supply Manual has moved to the CanadaBuys website. Check out the new landing page for the Supply Manual.

As part of the Acquisitions Program’s transformation agenda, PSPC is planning to archive and migrate the SACC manual to the CanadaBuys website. The SACC manual will continue to be available on the BuyandSell website to ensure continuity of service during this transition period. At this time, an initial version of the archived version of the SACC has been posted on CanadaBuys. We encourage you to go visit the site and get comfortable with the new format of the SACC at the following:

Archived - Standard Acquisition Clauses and Conditions Manual | CanadaBuys

We appreciate your continued feedback and cooperation during this transition.

Legal text for SACC item

Option 1

The Stop Work Order dated _____ and issued pursuant to section _____, Suspension of the Work of general conditions _____ is cancelled.

The Contractor must resume work in accordance with the Contract and inform the Contracting Authority immediately, in writing, if performance of the Work will be affected by the suspension.

The Contractor is entitled to be paid additional costs and expenses reasonably and properly incurred as a result of the suspension of the Work, plus a fair profit in accordance with the "Suspension of the Work" provision of the Contract. The Contractor must submit any claim he may have for payment of costs incurred as a result of the suspension, in writing, to the Contracting Authority.

Option 2

The Stop Work Order dated ____________ is cancelled.

The Contractor must resume work in accordance with the Contract and inform the Contracting Authority immediately, in writing, if performance of the Work will be affected by the suspension.