Improvement of Requirement During Solicitation Period

Attention! We’ve Moved! The Supply Manual has moved to the CanadaBuys website. Check out the new landing page for the Supply Manual.

Attention! As part of the Acquisitions Program’s transformation agenda, PSPC is planning to archive and migrate the SACC manual to the CanadaBuys website. The SACC manual will continue to be available on the BuyandSell website to ensure continuity of service during this transition period. At this time, an initial version of the archived version of the SACC has been posted on CanadaBuys. We encourage you to go visit the site and get comfortable with the new format of the SACC at the following:

Archived - Standard Acquisition Clauses and Conditions Manual | CanadaBuys

We appreciate your continued feedback and cooperation during this transition.

Item Information

Revision History

Date Status ID Title
2007-05-25 Active A9076T Improvement of Requirement During Solicitation Period (2007-05-25) A9076T

Remarks – Recommended Use of SACC Item

Use the following clause in bid solicitations to advise bidders that they could propose improvements to the technical requirements contained in the bid solicitation.

Legal text for SACC item

Should bidders consider that the specifications or Statement of Work contained in the bid solicitation could be improved technically or technologically, bidders are invited to make suggestions, in writing, to the Contracting Authority named in the bid solicitation. Bidders must clearly outline the suggested improvement as well as the reason for the suggestion. Suggestions that do not restrict the level of competition nor favour a particular bidder will be given consideration provided they are submitted to the Contracting Authority at least __________ days before the bid closing date. Canada will have the right to accept or reject any or all suggestions.