Legal text for SACC item
- The Contractor must provide a detailed project schedule in __________ (insert "network", "Gantt chart", or "detailed bar chart") format to the Contracting Authority and the _______ (insert "Technical", "Project", or "Inspection") Authority _______ (insert spelled out number) (_____) (insert number) weeks after award of Contract. This schedule must highlight the specific dates for the events listed below and all items listed in Annex _____ .
- The Contractor's schedule must include target dates for each of the following significant events:
- _________;
- _________;
- _________;
- _________;
- _________;
- _________;
- _________.
(Option: Contracting officers may include the following paragraph, but are advised that any update to the Contractor's schedule would then constitute an amendment to the Contract.)
- The schedule is to be regularly updated and available in the Contractor's office for review by Canada's authorities to determine the progress of the Work.